Roadway Reconstruction of 54 Street

(52 - 54 Avenue)

 

Partially Funded by:

Alberta Transportation logo

Project Profile:

The 2002 City of Camrose Capital Budget includes the roadway reconstruction of 54th Street between 52nd and 54th Avenue's and 52nd Avenue and 53rd Avenue’s between 53rd and 54th Streets.

Water and sewer service replacements were completed on the south block of  54th Street late last fall, and the north block will be completed this Spring. In both cases we allow at least one freeze thaw cycle to assist in the settlement. Thus the north block will not see paving until 2003.

The roadway project the excavation of the existing road base as required, installation of new concrete curbs and sidewalks, asphalt paving and boulevard sod work.

The City will host an open house for residents on 54th Street to discuss the local improvement costs, project schedule and input from property owners about existing problems such as drainage, access issues during construction, etc.

54th Street will be closed to vehicle traffic on a block by block basis during construction. Fortunately lanes provide an alternative access in these areas.

  

Engineering

Design and site supervision of this project will be conducted by the City Engineering Department.

 

Contractor

Branco Concrete and Border Paving were awarded contracts for this project.

 

Budget and Funding

 

The 2002 roadway local improvement project is estimated to cost $480,000.00 with approximately 1/3 being paid by the adjacent property owners and 2/3 paid by the City at large.

 

Total Project Cost

$480,000.00

City of Camrose Contribution

$  80,000.00
Local Improvement Costs $150,000.00

Provincial Grant

$250,000.00

Project subject to Local Improvement By-law being passed.

 

Schedule

The concrete replacement of curbs, gutters and sidewalks was completed in early September.Paving was completed by the end of September 2002.

Public Notice

For More Information Contact the Engineering Department at 672-4428.

  Home  Search  Index  Feedback  Privacy and Condition of Use StatementWe welcome your feedback
Updated February 4, 2005

Copyright © 2007 The City of Camrose
TM "The Rose City" and design is a Trademark the property of The City of Camrose

Copyright and Disclaimer | Conditions of Use and Privacy Statement