Welcome
Visitors
Community
City of Camrose
Admin
Leisure
Engineering
Protective

City Engineer | Building Inspection | Electrical Inspection | Engineering Services | Planning | Plumbing, Gas, Heating Inspection |Public Works

2008 Construction Program | 2007 Construction Program | 2006 Construction Program


54 Street

53 Avenue to 54 Avenue

Partially Funded by:

Infrastructure Canada Alberta Program

Project Profile:

The 2002 City of Camrose -Capital Budget included the roadway reconstruction of 54th Street between 52 and 54 Avenues and 52 Avenue and 53 Avenue's between 53 and 54 Streets.

Water and sewer service replacements were not completed on the north block of 54 Street until mid summer 2002. As the City allows at least one freeze / thaw cycle to assist in the settlement the north block will not see paving until the summer of 2003.

The roadway project involved the excavation of the existing road base 2002, followed by the installation of new concrete curbs & sidewalks, asphalt paving and boulevard sod work (2003).

The City hosted an open house for residents on 54 Street to discuss the local improvement costs, project schedule and get input from property owners about existing problems such as drainage, access issues during construction etc.

The north block of 54th Street (53-54 Ave) will be closed to vehicle traffic during the construction. Fortunately back alleys provide an alternative access in these areas.

54 Street Project Layout

Engineering:

The design and site supervision of this project will be conducted by the City Engineering Department.

Contractor:

Branco Concrete and Border Paving were awarded contracts for this project in 2002. These contracts will be extended to complete the project.

Budget and Funding:

Total Project Cost$145,000
City of Camrose Contribution$20,000
Local Improvement$32,000
Infrastructure Canada Alberta Program$93,000

Schedule:

54 Street54 Street
Existing sidewalk removed.Preparing equipment to excavate boulevard.
54 Street54 Street
Sidewalk completed on west side of 54 street.Concrete being poured and levelled off into the forms.
54 Street54 Street
Curb and gutter completed on west side of 54 street.Concrete being poured and levelled off into curb and gutter forms.
54 Street
Paving completed end of August.

Public Notice:

For More Information Contact the Engineering Department at 672-4428.

  Home  Search  Index  Feedback  Privacy and Condition of Use StatementWe welcome your feedback
Updated February 4, 2005

Copyright © 2007 The City of Camrose
TM "The Rose City" and design is a Trademark the property of The City of Camrose

Copyright and Disclaimer | Conditions of Use and Privacy Statement