Rosebud Area (41-46 Streets / 52-52b Avenue)

Partially Funded by:

Alberta Transportation logo

Project Profile:

Camrose City Council committed to undertake the roadway reconstruction in this area of Camrose within the next two years.

With this large a commitment by the City of Camrose, Council felt that the bylaw for replacing the curbs, sidewalks and roadway paving as a local improvement must be passed by area residents prior to proceeding with deep utility upgrades (water & sewer) which begun in the fall of 2004 and will continue in 2005.

Roadway improvements will begin in 2005 and continue in 2006, on blocks that had utility upgrades in 2004 / 2005 after allowing at least one year for the majority of trench settlement to occur. By delaying surface improvements we minimize concrete cracking and "dips" in road surface resulting in a higher quality product.

The City hosted an open house for residents on of the area in the spring of 2004 to discuss the local improvement costs, project schedule and get input from property owners about existing problems such as drainage and access issues during construction.


Rosebud Area (41-46 Streets / 52-52b Avenue)

Engineering:

The design and site supervision of this project is being conducted by the City Engineering Department.

Contractor:

Central Oilfield Services Ltd. was awarded the contract for underground work.
Joe's Concrete Services Ltd. was awarded the contract for the concrete work.
Border Paving Ltd. was awarded the paving contract.

Budget and Funding:

The 2005 / 2006 roadway component of this project is estimated to cost $1,734,000.00 with approximately $450,000.00 paid by the adjacent property owners.

Schedule:

  • Road work from the 2004 component began in late August and included landscaping and road base construction. Concrete work and paving were completed in October.
  • Remaining underground work began in mid August 2005 with completion expected in the spring of 2006.
  • The corresponding road work for the 2005 underground component is scheduled for 2006.

Photos:

May 6 - Installation of fire hydrant at the corner of 46 Street and 52B Avenue.May 6 - Coring out the road in order to install water and sewer mains.
May 10 - Installation of the 200mm watermain.May 14 - Installation of 900 diameter storm line on 52B Avenue.
Aug 29 - Coring of 43 Street.Sept 14 - Section of completed curb, gutter and sidewalk.
Sept 21 - Excavation of existing sidewalk, curb and gutter taking place.Sept 21 - Installation of curb forms.
Sept 30 - Pouring of remaining curb, gutter and sidewalk.

Public Notice:

For More Information Contact the Engineering Department at 672-4428.

  Home  Search  Index  Feedback  Privacy and Condition of Use StatementWe welcome your feedback
Updated November 17, 2005

Copyright © 2007 The City of Camrose
TM "The Rose City" and design is a Trademark the property of The City of Camrose

Copyright and Disclaimer | Conditions of Use and Privacy Statement