2008 Construction Program
| 2007 Construction Program
| 2006 Construction Program
48 Avenue / 66 Street Signal Upgrade
Last Modified Dec 12, 06
Project Profile:
Please see the 2005 component for project history.
2006 component of this project involves the geometric modifications to the curb, gutter & sidewalk.
Re-alignments will provide motorists traveling north
& south through this intersection with a smoother transition including safer truck movements north bound
off 48th Avenue.
Engineering:
The design and site supervision of this project will be conducted by the City Engineering
Department and Traffic Solutions Consulting Ltd.
Contractor:
Jo's Concrete Services Ltd. was awarded the contract for the curb and gutter replacement.
Border Paving Ltd. was awarded the contract for the overlay paving.
Budget and Funding:
The cost for this component of the project is $50,000.
Schedule:
Excavation of the existing curb, gutter and sidewalk and installation of the new curb, gutter, sidewalk and concrete
road base was completed by mid June. Paving was completed by mid June. Installation of traffic detection loops,
line markings and landscaping are scheduled for spring 2007.
Photos:
 |  |
| June 7 - Excavation of existing curb and gutter has been completed. | June 9 - Installation of the new curb and gutter completed. |
 |  |
| June 13 - Forming of new concrete sidewalk. | June 13 - Completed concrete sidewalk. |
 |  |
| June 14 - Completed concrete road base. | June 14 - Completed concrete road base. |
 |  |
| June 19 - Asphalt installation complete. | June 19 - Line markings and landscaping to follow. |
Public Notice:
For more information contact the Engineering Department at 672-4428.
|