Camrose Drive Rehabilitation Exhibition Drive to Highway 13
Last Modified Aug 22, 06
Partially Funded by:
Project Profile:
Accelerating asphalt distress/failures and the associated high maintenance costs involved have brought this
project to the top of the City's priority list with this being the third and final component of the Camrose Drive Rehabiliation project.
To make sufficient repairs to the existing asphalt, planing (grinding) of a layer of asphalt
road surface is required in an effort to mitigate much of the surface cracking you see today. The depth
of grinding and thickness of the new asphalt overlay will vary depending on the existing condition and
the extent of cracking.
Sections of Camrose Drive will be closed to vehicles for short periods during the construction.
Adjacent roadways will provide an alternative access.
The City will provide notice of the upcoming work in an effort to minimize the impact to the motoring public.
Engineering:
The design and site supervision of this project will be conducted by the City Engineering
Department, with the assistance of Infrastructure Systems Ltd..
Contractor:
Border Paving Ltd. was awarded the contract for this project.
Budget and Funding:
| Total Project Cost | $650,000 |
| City of Camrose Contribution | $250,000 |
| Provincial Grants | $400,000 |
Schedule:
Paving and line marking installation completed July.
Photos:
 |  |
| July 8 - Road oiled in preparation for paving. | July 8 - Road oiled in preparation for paving. |
 |  |
| July 12 - Placing of final lift asphalt. | July 12 - Compacting of final lift asphalt. |
 |  |
| July 12 - Road oiled in preparation for paving. | July - Paving and line markings completed. |
Public Notice:
For more information contact the Engineering Department at 672-4428.
|