Welcome
Visitors
Community
City of Camrose
Admin
Leisure
Engineering
Protective

City Engineer | Building Inspection | Electrical Inspection | Engineering Services | Planning | Plumbing, Gas, Heating Inspection |Public Works

2008 Construction Program | 2007 Construction Program | 2006 Construction Program


Rosebud Area
41 to 46 Streets and 52 to 52B Avenues

Last Modified Dec 12, 06

Project Profile:

Please see the 2004 and 2005 components for project history.

The 2006 component of this project involves completion of the 2005 underground water utility installation and the remaining replacement of concrete curb, gutter and sidewalk. This will be followed by asphalt paving later this fall.

Engineering:

The design and site supervision of this project will be conducted by the City Engineering Department.

Contractor:

Central Oilfield Services Ltd. was awarded the contract for the underground work.
Joe's Concrete Services Ltd. was awarded the contract for the concrete work.
Border Paving Ltd. was awarded the contract for the paving.

Budget and Funding:

Total Project Cost$1,500,000
City of Camrose Contribution$1,056,000
Local Improvement$444,000

Schedule:

Underground work was completed by early July.
Excavation of the roads is complete.
Concrete curb, gutter and sidewalks are 80% complete. Remaining concrete work is scheduled for May 2007.
Paving will immediately follow the completion of the concrete work.

Photos:

May 23 - Installation of the 750mm storm main on 52B Avenue between 43 and 44 Street. May 30 - Installation of the 750mm storm main on 52B Avenue between 43 and 44 Street.
June 12 - Backfilling with gravel for under the pipe stability to prevent "sagging". June 12 - Fitting the new pvc sewer main to match the old clay main.
June 12 - Installation of the 1200mm barrels to bring the top of the man hole up to road grade. July 13 - Excavation for curb and gutter installation.
August 18 - Completed concrete curb and gutter. August 18 - Forming and pouring of concrete sidewalks.
September 30 - Excavating existing curb and gutter. September 30 - Completed concrete sidewalk and excavated curb and gutter.
October 23 - Installation of concrete curb and gutter. October 23 - Completed concrete curb and gutter.

Public Notice:

For more information contact the Engineering Department at 672-4428.

  Home  Search  Index  Feedback  Privacy and Condition of Use StatementWe welcome your feedback
Updated December 12, 2006

Copyright © 2007 The City of Camrose
TM "The Rose City" and design is a Trademark the property of The City of Camrose

Copyright and Disclaimer | Conditions of Use and Privacy Statement