Project Profile:
The left turn lanes at these intersections on 48th Avenue are showing signs of distress due to larger than
normal truck turning movement. The City of Camrose Engineering Services Department is suggesting that a "white topping"
concrete inlay be installed.
The City of Camrose has used the "white topping" construction technique at other locations on 48th Avenue
with good success, most notably the left turn lane off 48th Avenue at 51 Street (Co-op Hill). For more
information about this, please read this
article
on the Cement Association of Canada website.
The construction involves the removal of approximately 100mm of the asphalt pavement and the installation of a
modified concrete mix specifically designed for this purpose.
48 Avenue and 68 Street Intersection

48 Avenue and 39 Street Intersection
Engineering:
The design and site supervision of this project will be conducted by the City Engineering
Department.
Contractor:
To be determined.
Budget and Funding:
This project is estimated to cost $80,000.
Schedule:
A new type of traffic sensor will be employed in this area. This project is now scheduled for late summer.
Public Notice: