Trunk Sewer Main Replacement
CNR to 44 Avenue

Last Modified Jul 17, 08

Project Profile:

The Sewer Master Plan study concluded that the trunk sewer along Camrose Creek would need to be upgraded due to age related deterioration and for future line capacity reasons.

The Sewer Main Replacement project involves the installation of 400 meters of 1200mm diameter trunk sewer along the Camrose Creek valley corridor from the CNR underpass on 50 Street to just north of 44 Avenue.

Because of the sensitive nature of this area, every reasonable effort will be made to limit damage in the Valley, and to insure that disturbed areas are rehabilitated appropriately.

Trunk Main Replacement

Engineering:

The design and site supervision of this project will be conducted by the City Engineering Department and Associated Engineering.

Contractor:

Nu Edge Construction has been awarded the contract for this project.

Budget and Funding:

The total project budget is $873,500 with funding from City reserves and utility rates.

Schedule:

This project is scheduled to begin in early summer 2008.

Public Notice:

For more information contact the Engineering Department at 672-4428.

  Home  Search  Index  Feedback  Privacy and Condition of Use StatementWe welcome your feedback
Updated July 17, 2008

Copyright © 2007 The City of Camrose
TM "The Rose City" and design is a Trademark the property of The City of Camrose

Copyright and Disclaimer | Conditions of Use and Privacy Statement